Engineering and construction of the Lynas Advanced Materials Plant (LAMP) in Malaysia remains on time and within budget as at 30 June 2010; with the first feed to kiln at the LAMP on target for the third quarter of 2011.
Site activities at the Lynas Advanced Materials Plant (LAMP) in the past quarter ramped-up in preparation for construction works reaching full capacity during the third quarter. The key activities of the second quarter revolved around the mobilisation to site of the main contractors for the construction of the plant, with the focus on engineering and procurement activities being to provide these construction resources with the information that they require to complete their tasks.
ENGINEERING AND PROCUREMENT
Engineering progressed during the quarter and the LampsOn alliance team between UGL and Lynas reported engineering remained on schedule for the LAMP as at the end of the second quarter. With the major concrete drawing production well underway, attention is now transferring to the issue of steel design to shop detailers directly from the three dimensional engineering model prior to fabrication.
During the second quarter Lynas investigated bringing in an experienced operator for the construction and operation of the Water Treatment Plant in Malaysia. Lynas has identified and selected Ranhill Water Technology to fulfil this role.
CONSTRUCTION
The major construction focus over the quarter has been the mobilisation of civil and concrete contractors to site and the commencement of civil works, including in-ground services and permanent site drainage, and the commencement of concreting activities, including the commissioning of wet and dry batch concrete plants.
In parallel with the mobilisation of contractors to site, the mobilisation of the construction management team has also progressed, with the relocation of key construction management personnel commencing and over 30 United Group Limited (UGL) personnel now mobilised to site.
Personnel for the Flue Gas Treatment Plant construction have been mobilised, with site establishment works having commenced. Personnel have also been mobilised for the commencement of construction of the pre-engineered buildings.
The cutting of piles is approximately 30% complete, with blinding slabs poured in the first process buildings in preparation for the first structural slabs to be poured in early July.